To see the variance between the Work and Baseline fields, review the Variance field. For finished…

To see the variance between the Work and Baseline fields, review the Variance field. For finished…

To see the variance between the Work and Baseline fields, review the Variance field. For finished tasks, this variance represents the difference between actual and planned work. For tasks currently in progress, the Work field is the total of Actual Work and Remaining Work. For tasks not yet started, the Work field is the current projection, and is often the same as the Baseline.

The Variance field compares just the Work and Baseline fields; it does not compare other baseline fields (such as Baseline1, Baseline2, and so on).